Project story
Adrian Taylor the interior designer took the brief of Steve Pilling and produced plan layouts, elevations and design drawings as part of a competitive tender package won by Select Interiors Ltd.
The project programme was five-week for refurbishment to include the following works: Demolition, mechanical, electrical, data, plaster finishes, bespoke joinery, extensive refurbishment of the Oak flooring, stone flags, lighting, signage and upholstery.